Crawley High Street

Location – Former Bar Med, 100 High St RH10 1BZ
Main Contractor – Mclaren Group
Client – Land Securities
Architect – Lyons Sleemans Hoare
Completion – November 2013

Squire energy had an early Involvement with Land Securities and Mclaren Group in securing an adequate gas volume required for a 110 bed hotel, a superstore and 4 restaurants. The first stage to this project included isolation of the current service and the removal of the meters in the building that was to be demolished. After this process was complete there was a requirement for the mains to be diverted and then for new gas supplies and metering to be implemented within the new buildings. Currently the services have been isolated, the meters removed and the mains diverted, allowing Southern Gas Networks to reinforce the mains, which in turn will allow the new supplies and gas meters to be installed within the complex.